The following preliminary proposed chronology was updated by Leyland Alliance in the June 2007 draft Development Agreement.
2006 |
| Sept |
City & Leyland Alliance Execute Exclusivity & Planning Agreement |
| Oct |
Leyland Alliance & City Contract with Charrette Planner (DPZ) |
| Oct - Jan 2007 |
Leyland Alliance Performs Due Diligence & Prepares for Charrette Preparation of Appraisals to Determine Fair Market Value of Properties, Environmental Testing, Feasibility Analyses |
2007 |
| Feb 7 |
Charrette Planning Process Complete |
| April 10 |
Final Charrette Report |
| June |
Development & Land Disposition Agreements |
July |
- Submission of Applications for Zoning, LWRP and/or Master Plan Amendments
- City Designation of Intent to Assume Lead Agency Status for Coordinated Review
-
Declaration of Lead Agency & Adoption of Positive Declaration
- Referrals of Zoning Amendments to Planning Board, Waterfront Advisory Committee, Architectural Review Commission and County Planning Department (GML Review)Reports required within 30 days
|
| July-Aug |
Applicant Submission of Draft Scoping Document Under SEQRA Referral of Draft Scoping Document to Involved Agencies |
| Aug-Sept |
Scoping Sessions |
| Sept |
Acceptance of Final Scoping Document |
| Sept-Dec |
Preparation of Draft Environmental Impact Statement (DEIS) |
| Dec |
Submission of Preliminary DEIS |
2008 |
| Jan |
Notice of Completion of DEIS |
| Feb |
Joint Public Hearings on DEIS, Zoning, LWRP and/or Master Plan Amendments |
| Mar-Apr |
Prepare & Submit Draft Final Environmental Impact Statement (FEIS) |
| May |
Notice of Completion of FEIS & Public Hearing on FEIS (optional) |
| July |
Adoption of SEQRA Findings Statements |
Aug |
- Adoption of Zoning, LWRP and/or Master Plan Amendments
- Amend Land Disposition Agreement
|
Sept-Oct |
- NYS Department of State Review and Referral of Proposed LWRP Amendment Other Agencies With Waterfront Jurisdiction
- Conveyance of Land (?)
|
Sept 2008 through Feb 2009 |
Submission & Review of Applications for Governmental Permits/Approvals:
- City Planning Board Site Plan Approval & Possible Subdivision
- Review of Preliminary Plat & Technical Issues
- Referrals
- County Planning Department
- WAC (30-day Consistency Review)
- ARC (Viewshed & Historic Overlay review and approval)
- Public Hearing (max. 120 days)
- Preliminary Plat Approval (w/in 62 days of close of public hearing)
- Final Plat Submission, Review & Public Hearing
- Final Approval
- NYS Department of Environmental Conservation
- NYS Department of Health
- Orange County Department of Health (Realty Subdivision)
- US Army Corps of Engineers (Nationwide Permits for dredging, shoreline activity and/or wetland)
- US EPA (Consent Decree or Site Deletion from NPL) February 2009 Final Approvals From Involved Agencies
|
2009 |
Feb |
Final Approvals From Involved Agencies |